INSTALLATION INSTRUCTIONS FOR CAST IRON FACADE KITS
Model Numbers LSS-CA35 (H0378) and LSS-CA40 (H0398)
FOR USE WITH SPECTRA LSS SERIES GAS FIREPLACES
GENERAL INFORMATION
Step 3. Hook the two cast iron side pieces onto the fireplace side
channels as shown in Figure 2. If the fit is too tight or loose,
adjust the gap of the two holding screws. (See Figure 1.)
These cast iron facade kits are designed to be used in conjunction with
the grillwork kits. Together, when installed, these kits complete the front
aspect of the Spectra LSS series gas fireplaces. The kits contain one
of each of the following cast iron facade pieces: bottom, top, left and
right piece. They also contain four 1/2 inch long 1/4-20 facade holding
screws, four 1-1/2 inch long 1/4-20 facade holding screws and these
instructions.
Side Piece
Cast iron side piece screw head
hooked behind top portion of shown
fireplace side channel detail
INSTALLATION INSTRUCTIONS
(top and bottom same method).
Step 1. Install the top and bottom grills to their corresponding top
and bottom cast iron facade pieces as detailed in the
installation instructions provided with the grillwork kits.
Step 2. Install four kit-provided facade holding screws to each of the
two side pieces ensuring compliance with the gaps shown in
Figure 1.
1/2 inch long Cast Iron Side Piece Holding Screws
3/32 inch
1-1/4 inch
(2.38 mm)
(31.8 mm)
Note: The left cast iron side piece (shown above) is sloped upward
at the top, from left to right, to form a mating fit to the arched cast iron
top piece. The right cast iron top piece has the opposite slope at the top.
Figure 2
Installing Cast Iron Side Pieces
1-1/2 inch long Cast Iron Bottom Piece Holding Screws
1/2 inch long,
1/4-20 Facade Holding Screws
1-1/2 inch long,
1/4-20 Facade
Holding Screws
Cast Iron Side Piece
Figure 1
Screw Head to Facade Side Piece Gap